Question: The next sprint starts - - - - - - - - - - - - - - - - - - - - -
The next sprint starts
Question options:
A
Only after the team for the next sprint is on board.
B
Only after the product increment is released to production.
C
Only after the retrospective event of the current sprint.
D
Only after the sprint planning.