Question: The normal and crash duration with cost for various activities involved in a repair work is given below. The direct cost for supervision of the

The normal and crash duration with cost forThe normal and crash duration with cost for

The normal and crash duration with cost for various activities involved in a repair work is given below. The direct cost for supervision of the work is also indicated. Task Pred Optimistic (Days) Most likely (Days) Pessimistic (Days) Crash Time (Days) Resource 1 (L.E) Res 2 (Workers) B 15 6 19 8 16 8 17 7 15 8 2 2 3 1 2 D 14 8 1 3 6 B 1 Crash Cost Res 1 (L.E) 230 170 880 250 65 75 180 880 210 320 825 420 4 E F G H | J K L 15 6 11 5 1 3 5 14 3 2 8 4 B,D C.E F G,H,1 G,H,1 J @ 100 150 120 100 50 40 140 100 150 200 200 200 3 5 6 26 6 6 19 5 3 2 1 1 18 4 3 2 11 4 3 13 6 4 15 8 3 3 The administrative cost of the project is L.E 198 per day. V- What is the standard deviation of the project? vi- What is the normal completion time for the project? vii- What is the probability of completing the project in 52 days? viii- Draw the Gantt Chart for resource 2 based on ES times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!