Question: The normal time for a work cycle in a worker - machine system is 6 . 2 7 min. For setting the standard time, the

The normal time for a work cycle in a worker-machine system is 6.27min. For setting the standard time, the PFD allowance factor is 12%, and the machine allowance factor is 25%. The work cycle includes manual elements totaling a normal time of 5.92min, all but 0.65min of which are performed as internal elements. Determine
(a) The standard time for the cycle
Machine time per cycle in minutes Tm=
Internal normal time in minutes Tnwi=5.3
Standard time in minutes Tstd=
(b) The daily output at standard performance.
Daily units produced in pieces Qstd=1.6
 The normal time for a work cycle in a worker-machine system

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!