Question: The optimistic, most likely and pessimistic activity times for A are 2 , 4 , and 6 days, respectively. The expected time of A is:

The optimistic, most likely and pessimistic activity times for A are 2,4, and 6 days, respectively. The expected time of A is:
The optimistic, most likely and pessimistic activity times for A are 2,4, and 6 days, respectively. The expected time of A is:
4
2
12
1