Question: Answer both questions for 100% feedback!! QUESTION 6 The optimistic, most likely and pessimistic activity times for A are 3, 4, and 5 days, respectively.

Answer both questions for 100% feedback!!

Answer both questions for 100% feedback!!

QUESTION 6 The optimistic, most likely and pessimistic activity times for A are 3, 4, and 5 days, respectively. The variance of activity time of Ais: O a 0.44 b. 0.11 c. 0.33 d. 0.67 QUESTION 7 The optimistic, most likely and pessimistic activity times for A are 2, 4 and 6 days, respectively. The variance of activity time of Ais: a. 0.67 b. 2.67 O c. 0.44 O d. 1