Question: The optimistic time for a task is 5 days, the most likely time is 6 days, and the pessimistic time is 13 days. The expected

  1. The optimistic time for a task is 5 days, the most likely time is 6 days, and the pessimistic time is 13 days. The expected time for the task is?

    7 days

    8 days

    5 days

    9 days

    6 days