Question: The outputs of the _ _ _ _ _ process include change request status updates, project management plan updates, and project document updates. Question 4

The outputs of the _____ process include change request status updates, project management plan updates, and project document updates.
Question 4 options:
executing
initiating
monitoring and controlling
planning