Question: The outputs of the _ _ _ _ _ process include change request status updates, project management plan updates, and project document updates. a .
The outputs of the process include change request status updates, project management plan updates, and project document updates.
a
Initiating
b
Planning
c
Executing
d
Monitoring and controlling