The owner of Kat Motel wants to develop a time standard for the task of cleaning a
Fantastic news! We've Found the answer you've been seeking!
Question:
OBSERVATION123456
TIME (SECONDS)998790819390
What is the standard time (ST) for this task if the employee worked at a fifty percent faster pace than is average, and an allowance of ten percent of the workday is used
a 100 sec
b 168.8 sec
c 90 sec
d 99 sec
e 150 sec
Related Book For
Introduction to Managerial Accounting
ISBN: 978-1259105708
5th Canadian edition
Authors: Peter C. Brewer, Ray H. Garrison, Eric Noreen, Suresh Kalagnanam, Ganesh Vaidyanathan