The person working on task C tells the project manager he can't start work until one day after the scheduled starting date. What impact would this have on the completion date of the project? Why? 2. Task A will
Transcribed Image Text:
The person working on task C tells the project manager he can't start work until one day after the scheduled starting date. What impact would this have on the completion date of the project? Why? 2. Task A will be delayed by 2 days because some equipment has arrived late. If the project manager still wants to finish the project within the original time frame, he will need to shorten the time for one or more of the tasks. What steps can he take to reduce the number of days allocated to a task? 3. The project manager decides to reduce the time needed for tasks D and F by one day each. How effective will this reduction be in achieving his aim of maintaining the original finish time for the project? The person working on task C tells the project manager he can't start work until one day after the scheduled starting date. What impact would this have on the completion date of the project? Why? 2. Task A will be delayed by 2 days because some equipment has arrived late. If the project manager still wants to finish the project within the original time frame, he will need to shorten the time for one or more of the tasks. What steps can he take to reduce the number of days allocated to a task? 3. The project manager decides to reduce the time needed for tasks D and F by one day each. How effective will this reduction be in achieving his aim of maintaining the original finish time for the project? Activity A B с D E F G H I J K L M N O Predecessor A A B D,E D,E B с C,F G H I J.K.L M Days 1 2 4 2 2 4 2 3 2 5 4 2 4 4 2 Activity A B с D E F G H I J K L M N O Predecessor A A B D,E D,E B с C,F G H I J.K.L M Days 1 2 4 2 2 4 2 3 2 5 4 2 4 4 2
- Expert Answer
1 If the person working on task C cannot start until one day after the scheduled starting date it would likely result in a delay in the completion dat View the full answer

Related Book For
Materials Science and Engineering An Introduction
ISBN: 978-0470419977
8th edition
Authors: William D. Callister Jr., David G. Rethwisch
Post a Question and Get Help
Cannot find your solution?
Post a FREE question now and get an answer within minutes*.
*Average response time.
Posted Date: June 01, 2023 05:56:28