Question: Given the activity table below, please prepare its corresponding Gantt chart and PERT diagrams. After which, answer the questions following the table. Activity Predecessor Days

Given the activity table below, please prepare its corresponding Gantt chart and PERT diagrams. After which, answer the questions following the table.

ActivityPredecessorDays
A- - - -1
B- - - -2
CA4
DA2
EB2
FD, E4
GD, E2
HB3
IC2
JC, F5
KG4
LH2
MI4
NJ, K, L4
OM2

  1. How many possible paths are there from the start to the end of the project?
  2. Which tasks are on the critical path of the PERT chart above?
  3. What is the slack time for tasks C, D and G?
  4. The person working on task C tells the project manager he can't start work until one day after the scheduled starting date. What impact would this have on the completion date of the project? Why?
  5. Task A will be delayed by 2 days because some equipment has arrived late. If the project manager still wants to finish the project within the original time frame, he will need to shorten the time for one or more of the tasks. What steps can he take to reduce the number of days allocated to a task?
  6. The project manager decides to reduce the time needed for tasks D and F by one day each. How effective will this reduction be in achieving his aim of maintaining the original finish time for the project?

Step by Step Solution

3.36 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ANSWER The answer provided below has been developed in a clear step by step manner Step 1 Explanatio... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!