Question: The pessimistic estimate for project completion is 6 0 weeks; the optimistic completion estimate is 3 6 weeks. With a most likely completion of 4

The pessimistic estimate for project completion is 60 weeks; the optimistic completion
estimate is 36 weeks. With a most likely completion of 48 weeks, what is the estimate for
the possible range of completion to a 95% confidence level?
a. Between 42 and 54 weeks
b. Between 38 and 58 weeks
c. Between 45 and 51 weeks
d. Between 40 and 56 weeks