Question: The Planned Value ( PV ) for a project is $ 4 0 0 , 0 0 0 , and the Earned Value ( EV

The Planned Value (PV) for a project is $400,000, and the Earned Value (EV) is $380,000. If the project has schedule performance index (SPI) of 0.95, what is the Actual Cost (AC) incurred for the project?
Question 43 options:
$390,000
$400,000
$370,000
$385,000
$365,000