Question: The PM receives a request that could require a complete redesign of a bridge project. What should the PM do next? Stop all work on

The PM receives a request that could require a complete redesign of a bridge project. What should the PM do next?
Stop all work on the bridge
Inform sponsors and customers that work must stop until the change is made
Inform the department that work has already started and cannot be stopped
Review the change and determine its impact on the project