Question: The PMBOK Guide 7 e introduces eight performance domains, groups of critical, related, even overlapping activities needed on all projects. In which of the performance
The PMBOK Guide introduces eight performance domains, groups of critical, related, even overlapping activities needed on all projects. In which of the performance domains would the project manager and team do the work to choose whether the project will be conducted using a predictive, hybrid, or adaptive methodology?
a Stakeholder Performance Domain
b Development Approach and Life Cycle Performance Domain
c Planning Performance Domain
d Delivery Performance Domain