Question: The point in time inside which changes to the master schedule typically must be approved by an authority higher than the master scheduler is referred
The point in time inside which changes to the master schedule typically must be approved by an authority higher than the master scheduler is referred to as the:
demand time fence.
planning time fence.
capabletopromise.
cutoff date.