The preliminary work sample of an operation indicates the following: Number of times operator working 50 Number
Fantastic news! We've Found the answer you've been seeking!
Question:
The preliminary work sample of an operation indicates the following:
Number of times operator working | 50 |
Number of times operator idle | 60 |
Total number of preliminary observations | 110 |
What is the required sample size for a 99.73% confidence level within +/- 5% precision?
A. 1,350
B. 1,150
C. 981
D. 891
Related Book For
Operations Management Processes and Supply Chains
ISBN: 978-0134741062
12th edition
Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Posted Date: