Question: The primary purpose for identifying the critical path on a CPM network is to: Group of answer choices Indicate the greatest amount of total float
The primary purpose for identifying the critical path on a CPM network is to:
Group of answer choices
Indicate the greatest amount of total float available
Identify the longest continuous path with the minimum amount of time for overall completion
Indicate the activities that can be delayed
Compare the activities on the original network to the activities on the current network