Question: The primary reason that the project management team develops a schedule/time management plan is Select one: a. To estimate how long project activities will take
The primary reason that the project management team develops a schedule/time management plan is
Select one:
a.
To estimate how long project activities will take and assign resources to project activities
b.
To set clear guidelines as to how the project schedule will be developed, managed and controlled throughout the project's duration
c.
To demonstrate to the project sponsor that the team is hard working and knows about project management
d.
To breakdown the work packages in the WBS into smaller packages and determine project milestones