Question: The probability and impact matrix above represents a look-up table for prioritizing risks that get the most attention in your project. The color red has
The probability and impact matrix above represents a look-up table for prioritizing risks that get the most attention in your project. The color red has the highest priority, green has the lowest priority, and yellow has moderate priority in terms of risks that should be addressed. After interviewing experienced project participants, stakeholders, and subject matter experts, you compiled the table below that shows the impact and probability of occurrence of risks A through D. Using the probability and impact matrix above determine which of the risks shown in the table should get the most attention in your project. Risk Impact of Risk Probability of occurrence A Moderate 0.5 B Very High 0.3 C Low 0.7 D High 0.8 Question 7 options: B D C A