Question: The probability that the control chart indicates that the process is out of control when it was only a random variation is: (1) highly unlikely.

The probability that the control chart indicates

The probability that the control chart indicates that the process is out of control when it was only a random variation is: (1) highly unlikely. (II) known as the alpha risk. (III) the probability of making a Type 1 error. (IV) the total probability from the sampling distribution that falls outside of control limits. O I and IV O ) II, III, and IV O land 11 O ) I, III, and IV O II and