Question: The processing times for five jobs and their due dates are given for single machine scheduling below: Job 1 2 3 4 5 Processing time
The processing times for five jobs and their due dates are given for single machine scheduling below: Job 1 2 3 4 5 Processing time (Hours) 9 7 5 11 6 Due date (Hours) 16 20 25 15 40 i. Using the Shortest Processing Time (SPT) and Earliest Due Date (EDD) determine the job sequences. (5 Marks) ii. For each sequencing rule, evaluate its effectiveness in terms of average flow time, the average number of jobs in the system and average job lateness. (5 Marks) iii. Which sequencing rule do you recommend and why