Question: The Program Evaluation Review Technique (PERT) and critical path method (CPM) are two techniques that can help you with project management. Which of the following

The Program Evaluation Review Technique (PERT) and critical path method (CPM) are two techniques that can help you with project management. Which of the following statements is true regarding the PERT and CPM? These techniques were introduced in the 1950s by the U.S. Navy. These techniques are normally independent from each other and are not used together. These techniques are specialized for software projects. These techniques were introduced in the 1950s by the U.S. government to manage its National Aeronautics and Space Administration (NASA) space programs