Question: The project ABC given the following network with activity times in weeks Activity A B C D E F G H K I J Most
- The project ABC given the following network with activity times in weeks
| A | B | C | D | E | F | G | H | K | I | J |
| Most likely estimation | 18.5 | 16 | 11 | 12 | 17 | 9 | 8 | 9 | 12 | 10 | 9 |
| Optimistic estimation | 9 | 3 | 4 | 8 | 9 | 8 | 5 | 8 | 6 | 6 | 8 |
| Pessimistic estimation | 28 | 20 | 20 | 15 | 20 | 15 | 9 | 11 | 26 | 16 | 15 |
| Predecessor Activity | - | - | - | A | A | A | B, D | C | E | C | F, G, H |
- Determine the earliest start and finish times, latest start and finish times for each activity. (10 points)
- What is the value of total slack times? (show your works as well). (15 points)
- Indicate the critical path and the expected project completion time. (10 points)
Rank and name the three highest priority activities, explain why.