Question: The project baseline should change when . . ? A ) a high duration activity has finished out of sequence. B ) a change request

The project baseline should change when ..?
A) a high duration activity has finished out of sequence.
B) a change request is approved.
C) when productivity is higher or lower than estimated.
D) activities have taken longer than estimated.
 The project baseline should change when ..? A) a high duration