Question: The project baseline should change when . . ? Question options: A ) when productivity is higher or lower than estimated. B ) activities have
The project baseline should change when
Question options:
A
when productivity is higher or lower than estimated.
B
activities have taken longer than estimated.
C
a high duration activity has finished out of sequence.
D
a change request is approved.