Question: The project baseline should change when . . ? Question options: A ) when productivity is higher or lower than estimated. B ) activities have

The project baseline should change when ..?
Question options:
A)
when productivity is higher or lower than estimated.
B)
activities have taken longer than estimated.
C)
a high duration activity has finished out of sequence.
D)
a change request is approved.