Question: The project completion within 92 weeks a) Draw an AOA project network b)Find all possible paths from the start node to the end node. Compute

The project completion within 92 weeks a) Draw an

The project completion within 92 weeks

a) Draw an AOA project network

b)Find all possible paths from the start node to the end node. Compute the time required for each path. What are the minimum completion project time and the critical path?

Activity Immediate Predecessors Normal Time (Weeks) A 32 B 28 . 36 D B 16 E B 32 F B 54 G D 17 H 20 I E, G E,G C,F 34 J 18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!