Question: The project completion within 92 weeks a) Draw an AOA project network b)Find all possible paths from the start node to the end node. Compute

The project completion within 92 weeks
a) Draw an AOA project network
b)Find all possible paths from the start node to the end node. Compute the time required for each path. What are the minimum completion project time and the critical path?
Activity Immediate Predecessors Normal Time (Weeks) A 32 B 28 . 36 D B 16 E B 32 F B 54 G D 17 H 20 I E, G E,G C,F 34 J 18Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts