Question: The project defined by the following decision tree has a required discount rate of 17 percent. Cash Flow Afla Tas Invest $100.000.000 Success Yes $66.000.000
The project defined by the following decision tree has a required discount rate of 17 percent. Cash Flow Afla Tas Invest $100.000.000 Success Yes $66.000.000 yen Test Cost Do Not Invest NPV $0 $20,000,000 Friluce NPV-5-20.000.000 Do not test What is the Time O net present value of a successful test and investment? Multiple Choice $42,997,143 $32,288,788 $26.997,143 $21,565,903 $16.997143