Question: The project described in the table below is being considered. Managers have made estimates of the durations of the activities in weeks. a) Construct a

The project described in the table below is being considered. Managers have made estimates of the durations of the activities in weeks.The project described in the table below is being

a) Construct a project network

(b) Determine the critical path

(c) Determine the expected completion time of the project and the probability of achieving this time (Standard Normal Z Table Attached)

(d) Determine the probability of completing the project 2 weeks earlier (Standard Normal Z Table Attached) and comment on the additional risk involved

(e) Explain why Monte Carlo Simulation is used to calculate likely completion probabilities rather than the methods used in Parts C and D of this question, and briefly describe how the Monte Carlo Simulation is applied to project duration estimation.

Task predecessors A B A A D E B,C F D G D H E,F I E,F J I,G K H optimistic pessimistic most likely 4 8 5 5 10 7 8 12 11 2 7 3 4 10 7 6 15 9 8 16 12 5 9 6 3 7 5 5 11 8 6 13 9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!