The project described in the table uses the same resource for activities A, B, C, and D.
Fantastic news! We've Found the answer you've been seeking!
Question:
The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?
Activity | Duration | Predecessor | WBS ID |
W | 4 | -- | 12 |
A | 3 | W | 16 |
B | 4 | W | 15 |
C | 5 | W | 13 |
D | 6 | W | 14 |
E | 1 | B | 17 |
Z | 7 | A, E, C, D | 18 |
Activity A | ||
Activity B | ||
Activity C | ||
Activity D |