Question: The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource

The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?

ActivityDurationPredecessorWBS ID
W4--12
A3W16
B4W15
C5W13
D6W14
E1B17
Z7A, E, C, D18

Activity A

Activity B

Activity C

Activity D