Question: The project has been broken down into 10 activities with the following predecessors and duration Activity Predecessor Duration A - 3 B - 5 C

  1. The project has been broken down into 10 activities with the following predecessors and duration

Activity

Predecessor

Duration

A

-

3

B

-

5

C

B

3

D

A,C

4

E

D

8

E

F

2

G

F

4

H

F

2

I

B

5

J

H,E,G

3

Draw the network diagram and identify the critical path