Question: The project has been broken down into 10 activities with the following predecessors and duration Activity Predecessor Duration A - 3 B - 5 C
-
The project has been broken down into 10 activities with the following predecessors and duration
| Activity | Predecessor | Duration |
| A | - | 3 |
| B | - | 5 |
| C | B | 3 |
| D | A,C | 4 |
| E | D | 8 |
| E | F | 2 |
| G | F | 4 |
| H | F | 2 |
| I | B | 5 |
| J | H,E,G | 3 |
Draw the network diagram and identify the critical path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
