Question: The project is about zero-waste food. please write the duration and predecessors in the Microsoft project program for this topic and take a screenshot to

The project is about zero-waste food. please write the duration and predecessors in the Microsoft project program for this topic and take a screenshot to show me the network diagram and critical path of the program

WBS

Task Name

1

zero waste food

1.1

Market research

1.1.1

material research

1.1.2

verify the material

1.2

sponsor

1.2.1

conducting a sponsor

1.2.2

making an appoinment

1.2.3

conducting the negotiations

1.2.4

making an agreement with the sponsor

1.3

collaction

1.3.1

determine the restaurants

1.3.2

arranging meetings

1.3.3

making presentations

1.3.4

making an agreement

1.4

logistic

1.4.1

supplying the machine from abroad

1.4.2

transporting the purchased machine

1.4.3

contracting with the logistics company

1.4.4

determining the route to collect the waste food

1.4.5

collecting the waste food and transporting it

1.5

production

1.5.1

sorting the waste food

1.5.2

putting waste food into machine

1.5.3

measurement of obtained fertilizers

1.6

Test

1.6.1

Testing of production efficiency of machines

1.6.2

Esting of fertilizer quality

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!