Question: The project is about zero-waste food. please write the duration and predecessors in the Microsoft project program for this topic and take a screenshot to
The project is about zero-waste food. please write the duration and predecessors in the Microsoft project program for this topic and take a screenshot to show me the network diagram and critical path of the program
| WBS | Task Name |
| 1 | zero waste food |
| 1.1 | Market research |
| 1.1.1 | material research |
| 1.1.2 | verify the material |
| 1.2 | sponsor |
| 1.2.1 | conducting a sponsor |
| 1.2.2 | making an appoinment |
| 1.2.3 | conducting the negotiations |
| 1.2.4 | making an agreement with the sponsor |
| 1.3 | collaction |
| 1.3.1 | determine the restaurants |
| 1.3.2 | arranging meetings |
| 1.3.3 | making presentations |
| 1.3.4 | making an agreement |
| 1.4 | logistic |
| 1.4.1 | supplying the machine from abroad |
| 1.4.2 | transporting the purchased machine |
| 1.4.3 | contracting with the logistics company |
| 1.4.4 | determining the route to collect the waste food |
| 1.4.5 | collecting the waste food and transporting it |
| 1.5 | production |
| 1.5.1 | sorting the waste food |
| 1.5.2 | putting waste food into machine |
| 1.5.3 | measurement of obtained fertilizers |
| 1.6 | Test |
| 1.6.1 | Testing of production efficiency of machines |
| 1.6.2 | Esting of fertilizer quality |