Question: The project management information system, such as any automated system that can be utilized during the Direct and Manage Project Work process, will include all

The project management information system, such as any automated system that can be utilized during the Direct and Manage Project Work process, will include all the following EXCEPT: 
• A scheduling software tool 
• An information collection and distribution system 
• A configuration management system 
• A tool to identify the internal and external stakeholders

Step by Step Solution

3.53 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Solution The correct answer is A tool technique to identify the internal and external stakeholders ... View full answer