Question: The Inputs to the Direct and Manage Project Work Process include the following: A) The Project Management Plan along with its subsidiary Plans and Documents.
The Inputs to the “Direct and Manage Project Work” Process include the following:
A) The Project Management Plan along with its subsidiary Plans and Documents.
B) The Project Management Plan without its subsidiary Plans and Documents, but with the Approved Change Requests.
C) The Project Management Plan without any Enterprise Environmental Factors.
D) The Project Management Plan along with only its relevant Enterprise Environmental Factors.
ANSWER: A