The project management plan is complete and is ready to be baselined. However, a key stakeholder just discovered a critical omission and requests an adjustment to the PM plan. What should you do next as the project manager?
Implement a formal CR
Make the adjustment
Consult the change control board
Inform the stakeholder that this constitutes scope creep and refuse to make the change