Question: The project manager and team finished executing a software project. The deliverable passed quality assurance and was incorporated in the latest release: The project sponsor
The project manager and team finished executing a software project. The deliverable passed quality assurance and was incorporated in the latest release: The project sponsor liked the product and gave his formal acceptance and approval. What should the project manager do next?
Release the project team.
Begin working on the next project.
Complete the procurement management plan.
Conduct lessons learned.