Question: The project manager and team finished executing a software project. The deliverable passed quality assurance and was incorporated in the latest release: The project sponsor

The project manager and team finished executing a software project. The deliverable passed quality assurance and was incorporated in the latest release: The project sponsor liked the product and gave his formal acceptance and approval. What should the project manager do next?
Release the project team.
Begin working on the next project.
Complete the procurement management plan.
Conduct lessons learned.
 The project manager and team finished executing a software project. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!