Question: The project manager determined that a problem with electricity during hardware installation was the cause of an unfair verbal CPI. The electricity problem can no
The project manager determined that a problem with electricity during hardware installation was the cause of an unfair verbal CPI. The electricity problem can no longer occur. Which of the following should be the project manager used to calculate the project EAC?
Atypical EAC
Other projects as a reference
Typical EAC
Pessimistic EAC