Question: The project manager determined that a problem with electricity during hardware installation was the cause of an unfavorable CPI. The electricity problem can no longer

The project manager determined that a problem with electricity during hardware installation was the cause of an unfavorable CPI. The electricity problem can no longer occur. Which of the following should the project manager use to calculate the project EAC?

A. Typical EAC B. Atypical EAC C. Other projects as a reference D. Pessimistic EAC