Question: the project manager for a large project being developed in northern ontario recognizes that i will be necessary for her to maintain a close presence
the project manager for a large project being developed in northern ontario recognizes that i will be necessary for her to maintain a close presence at the construction site during its development and has negotiated the use of a building for her team near the contruction project. the cost of the building must be factored into the project cost and will increase with use, that is yhe cost of heating and other utilities is subject to change depending upon weather and in use. what type of cost would this building represent? A-variable direct B- indirect. C- nonrecurring D- none of the above