Question: The project manager for a large project being developed in northern Ontario recognizes that it will be necessary for her to maintain a close presence
The project manager for a large project being developed in northern Ontario recognizes that it will be necessary for her to maintain a close presence at the construction site during its development, and has negotiated the use of a building for her team near the construction project. The cost of the building must be factored into the project cost and will increase with use; that is, the cost of heating and other utilities is subject to change depending upon weather and team use. What type of cost would this building represent?
a. Variable direct
b. Indirect
c. Nonrecurring
d. None of the above
Step by Step Solution
3.45 Rating (161 Votes )
There are 3 Steps involved in it
aThe cost of using a s... View full answer
Get step-by-step solutions from verified subject matter experts
