Question: The project manager for a new product development project that has four levels in the work breakdown structure. The network diagram and duration estimates have

The project manager for a new product development project that has four levels in the work breakdown structure. The network diagram and duration estimates have been created, and a schedule has been developed and compressed. Which schedule management activity should you do next?
a
Control the schedule
b
Determine dependencies
c
Analogously estimate the schedule
d
Gain approval