Question: You are the project manager for a new product development project that has four levels in the work breakdown structure. The network diagram and duration
You are the project manager for a new product development project that has four levels in the work breakdown structure. The network diagram and duration estimates have been created, and a schedule has been developed and compressed. Which time management activity should you do NEXT?
A. Control Schedule.
B. Estimate Activity Resources.
C. Analogously estimate the schedule.
D. Gain approval.