Question: The project manager has completed the project management plan and sent it to the sponsor, other key stakeholders, and team leads for their approval. Upon
The project manager has completed the project management plan and sent it to the sponsor, other key stakeholders, and team leads for their approval. Upon review, one of the team leads notices an important activity is missing and requests that it be added to the project management plan. What should the project manager doAAdvise the team lead that adding the activity at this stage is gold plating.BSubmit a change request because the team lead has already performed the impact analysis and stated that the activity needs to be added.CO Perform an impact analysis of the missing activity.DAdd the missing activity to the project management plan.