Question: The Project Manager has identified work packages and added them to the WBS dictionary. Which process is the Project Manager undertaking? Group of answer choices

The Project Manager has identified work packages and added them to the WBS dictionary. Which process is the Project Manager undertaking?
Group of answer choices
Define Scope
Identify Requirements
Create WBS
Decomposition