Question: The project manager has made reference to the project charter when a blocker had been encountered to the implementation of the project. A project charter
The project manager has made reference to the project charter when a blocker had been encountered to the implementation of the project. A project charter includes all of the following EXCEPT:
A
Roles and responsibilities.
B
Authority of the project and the stakeholders.
C
Project goals and objectives.
D
Project tasks and activities.