Question: The project manager has received complaints from the software developers that requirements are being changed without them being notified or asked about potential impacts. The

The project manager has received complaints from the software developers that requirements are being changed without them being notified or asked about potential impacts. The business analysts believe that the developers were given outdated requirements that should not have been in the requirements matrix that the developers were working from. What tool can the project manager adopt to prevent this from happening in the future?
Question 4 options:
None of the listed choices are correct.
Version Control System
Requirements Tracking Tool
Configuration Management System

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!