Question: the project manager in a CONSTRUCTION project which is currently initiated, you want to assess high - level risks. What should you do ? Discuss
the project manager in a CONSTRUCTION project which is currently initiated, you want to assess highlevel risks. What should you do
Discuss the risks documented in your Risk register with the project key stakeholders.
Identify and analyze risk events using qualitative and quantitative techniques.
Develop the project charter and a risk management plan to start identifying risks based on those and other documents.
Develop contingency plans and fallback plans in case the original plan proves wrong.