Question: As the project manager in a software project which is currently initiated, you want to assess high - level risks. What should you do: a
As the project manager in a software project which is currently initiated, you want to assess highlevel risks. What should you do:
a Discuss the risks documented.
D Develop contingency plans and fallback plans in case the original plan proves wrong
c Develop the project charter and a risk management plan to start identifying risks based on those and other documents
d Identify and analyse risk events using qualitative and quantitative techniques