Question: The project manager just started leading a project team from which the project manager . After a quick evaluation of the project, it is apparent
The project manager just started leading a project team from which the project manager After a quick evaluation of the project, it is apparent that team morale is low due to about how to tasks. Tasks are taking longer than and the project is off schedule.Issue a change request to extend the project schedule based on identified delays.Inform the that the project will be delayed due to previous team management.Conduct a meeting with the project team to discuss and address the sources of disagreement.Crash the project timeline to ensure the project is back on schedule.PreWhat should the project manager do