Question: The Project manager of a task force planning the construction of an area stadium had hoped to be able to complete construction prior to the
The Project manager of a task force planning the construction of an area stadium had hoped to be able to complete construction prior to the start of the next college football season. Given the following time estimates, and the fact that the football season opener is in ten months (44 weeks), will the stadium be completed in time for the season opener? A. Draw the Activity on Node diagram B. Calculate the early start (ES), Early Finish (EF), Late Start (LS) Late Finish (LF) and Slack time (ST) for each activity C. Determine the critical Path in terms of activities and total time for critical path D. Draw a GANTT chart to use for this project E. Will the stadium be finished in time for the season opener football game?